    • Client: Federal Ministry Of Housing And Urban Development.
    • Duration of Contract: (2004)
    • Scope: Build & operate for 25 yrs. ONE block of 3 Floors of 105 Rooms Students Hostel at University of Nigeria, Nsukka.
    • Contract Value: N196m
    • Client: Rivers State Government
    • Duration of Contract: 4 months (2006)
    • Scope: Design and Construction 2 units of 50,000 Gallons Galvanized water Tank for Aggrey Road and Creek Road, Port Harcourt.
    • Client: Rivers State Government
    • Duration of Contract: 6 months (2000)
    • Scope: Construction of Twin Executive Duplex at Tombia, Rivers State.
    • Client: Rivers State Government
    • Duration of Contract: 6 months (2009)
    • Scope: Construction of Mmahum Water Scheme, Egbema.
    • Client: Rivers State Government
    • Duration of Contract: (2002)
    • Scope: Purchase of Materials, Installation of 500 KVA Substation, 11 KV & 415V Matriculations and 3KM Line for the Electrification of Model Industrial Estate at Tombia, Rivers State
    • Contract Value: N169m
    • Client: Saipem Nigeria Limited
    • Duration of Contract: 10 months (2007)
    • Scope: Geotechnical Services/Dredging works in the Swampy Areas of Bayelsa
    • Client: Mobil Producing Nigeria Unlimited
    • Duration of Contract: 13 months (2015-2016)
    • Scope: Maintenance of Air Cooling Systems At QIT
    • Client: Nigeria Agip Oil Company Limited
    • Duration of Contract: (2003)
    • Scope: Construction Sokalugbene Water Scheme
    • Client: Nigeria Agip Oil Company Limited
    • Duration of Contract: 2014
    • Scope: Supply Of Specialist Personnel
    • Client: VP Energy Limited
    • Duration of Contract: 12 Months (2013 - 2014)
    • Scope: Provision Of Manpower Services
    • Client:Lonestar Drilling Nig. Limited
    • Duration of Contract: 7 Months (2012)
    • Scope: Refurbishment Of Rig (Mechanical,Instrumentation,Electrical & Panelling)
    • Client: VP Energy Limited
    • Duration of Contract: 12 Months (2013 - 2014)
    • Scope: Design,Procurement And Installation Of Power Upgrade Systems
    • Client: Mobil Producing Nigeria Limited
    • Duration of Contract: 2014
    • Scope: Provision Of Scaffolding Services For Maintenance Operations
    • Client: West African Gas Pipeline Company Limited (WAGPCO)
    • Duration of Contract: 2014
    • Scope: Dismantling,Modification Of Caravans At WAGPCO
    • Client: West African Gas Pipeline Company Limited (WAGPCO)
    • Duration of Contract: 12 Months
    • Scope: Provision Of General Inspection Services At WAGPCO
    • Client: West African Gas Pipeline Company Limited (WAGPCO)
    • Duration of Contract: 17 Months (2014 - 2015)
    • Scope: Provision Of Piping, Modification And Mechanical Repairs Services At WAGPCO
    • Client: Niger Delta Development Commission(NDDC)
    • Year: 2013
    • Scope: Contract For The Construction Of Road Side Drains At Ikot Edor – Ukpana Road,Onna Lga,Akwa Ibom State
    • Client: Niger Delta Development Commission(NDDC)
    • Year: 2011
    • Scope: Contract For The Construction Of Afaha Ube Uyo Road,Akwa Ibom State